Research Article | | Peer-Reviewed

A Hybrid Approach Based on Factor Analysis and Fuzzy AHP Multi-criteria Decision-Making Model for Evaluating Pavement Maintenance Management Practices: The Case of Ethiopian Roads Authority

Received: 31 May 2025     Accepted: 19 June 2025     Published: 10 July 2025
Views:       Downloads:
Abstract

The construction industry has long been realized as one of the most important enablers for the social, economic, and political development of countries. Road pavement that has been constructed undergoes a process of deterioration and catastrophic failure after opening to traffic starts at a low rate and with time this rate increases because of aging, overuse, misuse, and mismanagement. Proper maintenance management practice helps to reduce the cost of maintenance and to make sure the pavement is in good condition with minimum maintenance. Thus, the study focuses on exploring the pavement maintenance management practice in the Ethiopian road authority. The method of data analysis for this study was carried out by using factor analysis and fuzzy AHP methods. Factor analysis provides as to reduce a data set to a more manageable size without much loss of the original information while fuzzy AHP is used to determine the preference weights of the variables. To achieve the objective, the data were collected from primary and secondary sources. SPSS software version 23, and Microsoft Excel were used as analysis tools. The study revealed that written maintenance management plans (0.072), maintenance staff training (0.071), maintenance management team leader (0.069), maintenance checklists (0.068), and periodic maintenance (0.063) were mostly practiced in the Ethiopian road authority. Finally, it can be recommended that the decision-makers conduct practical solutions to enhance, advance, and improve pavement maintenance management practices.

Published in Journal of Civil, Construction and Environmental Engineering (Volume 10, Issue 4)
DOI 10.11648/j.jccee.20251004.11
Page(s) 131-152
Creative Commons

This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited.

Copyright

Copyright © The Author(s), 2025. Published by Science Publishing Group

Keywords

Pavement, Maintenance Management, Factor Analysis, Fuzzy AHP

1. Introduction
The construction industry is a sector of the economy that transforms various resources into constructed physical economic and social infrastructure necessary for socio-economic development. It embraces the process by which the said physical infrastructure is planned, designed, procured, constructed or produced, altered, repaired, maintained, and demolished . The construction industry consists of various sectors. These are the building, transportation systems and facilities which are airports, harbors, highways, subways, bridges, and railroads. Roads and highways are a major part of the transportation infrastructure that play a substantial role in the local economy, community development, and, it provides a link between businesses, industries and consumers, it affects the development of economy and social activities for the country .
Efficient sustainable rural, urban and inter-urban transport infrastructure in combination with affordable transport services drive commerce, mobility and access to social services and underpin development in all countries. Roads, averaging 80% worldwide, dominate the transport sector in many countries and are principal means of passenger and freight movement . The pavement maintenance management system is a set of tools that helps decision maker to determine optimum strategies for existing pavement condition by evaluation and maintenance of the pavement to reserve an acceptable serviceability for a desired period of time . Poor pavement maintenance management practices lead the company to spend more money to maintain and repair the pavement .
The authors did not get any study that is the same as the current study while searching in the international journals as this study is almost unique of its kind and deals with pavement maintenance management practice in the Ethiopian road authority. The importance of road transport, it is important to identify maintenance of the pavement is important to make sure the traffic flows smoothly facilitate transport service, and reduce costs of travel and trade, enhancing accessibility to markets and services . This study offers a prolonged support to earlier investigation on the concept of maintenance management of pavement through the development of an advanced method of factor analysis and Fuzzy AHP methodologies. The methodology provides as to consider the human assessment of qualitative attributes is always subjective and thus imprecise. Thus, to model this kind of uncertainty in human preference, fuzzy sets could be incorporated with the pairwise comparison as an extension of AHP. Furthermore, the study provides a reference guide for the company in general to know the pavement maintenance management practice. Moreover, this study provides a secondary source of data for future users, academicians and policymakers shall also use this study to make further investigation on the topic as required and also it serves as a basis for further studies. This study aimed to explore pavement maintenance management practices. To achieve this study, there is a need to explore pavement maintenance management practices in the recent literature. Nowadays, it is accepted that the study on pavement maintenance management systems was rarely practiced in the road networks of Ethiopia; even though the studies on pavement maintenance management practice are very limited.
The rest of the paper is structured as follows: Section 2 presents pavement maintenance management practice and Section 3 present how the integrated methodology of factor analysis and fuzzy AHP can be adopted. Section 4 shows numerical analysis and results of factor analysis and fuzzy AHP results along with some discussions related to pavement maintenance management. Section 5 presents a discussion of the findings. Finally, general conclusions and remarks are then presented in Section 6.
2. Pavement Maintenance Management Practices
Pavement management, in its broadest sense, encompasses all the activities involved in the planning, design, construction, maintenance, evaluation, and rehabilitation of the pavement portion of a public works program . Pavement maintenance management practices identified in the literature can be defined as follows .
2.1. Maintenance Management Team
Maintenance management team provides the overall coordination of maintenance functions to meet the pavement maintenance requirement . Maintenance management team members to make sure that all works are going in the direction of the implementation of the strategic plans drawn for the maintenance organization.
1. Cooperation and Coordination of Maintenance Team: Maintenance coordination is an attempt at reaching an agreement on sharing tasks and responsibilities in working together in maintenance, focusing on identifying complementarities and possible interactions .
2. Responsible Maintenance Management Team: responsible maintenance management team sets the framework for maintenance to improve its effectiveness and efficiency .
3. Maintenance Organization Management: is responsible for managing the operations and maintenance of all the pavement facilities of the organization .
4. Maintenance Management Team Leader: provides leadership and line management to the team, coordinating and overseeing .
5. A Commitment of Maintenance Management Team: The commitment of the maintenance team plays a vital role in organizations as they drive the direction of the organization .
6. Maintenance Leadership: is responsible for establishing the policies and expectations that serve to guide maintenance and the maintenance organization in supporting maintenance activities .
7. Maintenance Management Team Meeting: Maintenance management team meetings among a client, consultant, and contractor shall be organized at regular intervals on maintenance management approaches .
8. Private Contractor Participation for Maintenance: The involvement of a private contractor in the construction project has a significant role in some maintenance work especially through using specialized out-source contractors .
9. Staffing Skilled Manpower: Skilled manpower has well-defined job roles, knows what is expected of them, the skills and knowledge as well as the resources to perform, and rewards for good performance .
10. Maintenance management team capacity and capability: Maintenance management team's capacity and capability determine the required resources for maintenance .
2.2. Maintenance Management Plan
The pavement maintenance plan has been prepared to the framework of guidance, standards, and performance management incorporated in the national code of practice for maintenance .
1. Written Maintenance Management Plan: A written maintenance management plan including maintenance policy, standard procedures, and strategy helps to provide sufficient maintenance management .
2. Strategic Maintenance Management Plan: Strategic maintenance management is the integration of your maintenance program into the business plans of the company for the least amount of production disruption while maintaining the road pavement .
3. Staff Involvement in Developing the Maintenance Plan: The involvement of staff members in the maintenance plan provides to maximize individual contributions to improving the best value service delivery .
4. Maintenance Management Plan Revision: Maintenance plan revision provides to ensure the information that may be useful for roads wishing to pursue the maintenance plan .
5. Budget for Financing Maintenance Programs: The pavement maintenance program needs an adequate budget to provide the road components and services required to make road maintenance work .
6. Maintenance Planning and Scheduling: focuses on the planning and scheduling of the routine, day-in and day-out maintenance.
2.3. Maintenance Approaches
Maintenance activities were performed on the actual state of an asset and evaluated any changes in the parameters of the asset with time . Based on their operational frequency maintenance activity is broadly categorized into two. These are Periodic and Routine maintenance. Periodic Maintenance: Periodic maintenance consists of the provision of a surfacing layer at regular intervals of time . Routine Maintenance: This maintenance covers items such as repairing of cracks and patch work, filling of potholes, maintenance of carriageways, maintenance of road signs . Based on their time of application maintenance is classified as Preventive Maintenance. Corrective Maintenance: Performed after a deficiency occurs in the pavement, such as loss of friction, moderate to severe rutting, or extensive cracking . Emergency Maintenance: Performed during an emergency, such as a blowout or severe pothole that needs repair immediately .
2.4. Maintenance Information and Communication Management
Maintenance information and communication are the most important components of maintenance management that are required to make any justification and decision .
1. Maintenance Checklists: Maintenance checklist is typically a list of maintenance actions arranged systematically to organize information of maintenance and instructions are supplied for maintenance evaluation .
2. Maintenance Staff Training: Maintenance training means investing in competitiveness, profitability, quality, and growth .
3. Schedule Maintenance Work: Schedule maintenance work is the planned hours of work over some time and it can be repeated continuously, subject to change following collective agreement .
4. Documentation and Recordkeeping: Documentation and recordkeeping are, formal documents, reports, notes, and written files of the organization about the maintenance of a certain piece of resources .
2.5. Maintenance Identification and Assessment
A variety of assessment mechanisms were used to determine the requirement through a variety of techniques as follows.
1. Identify and Categorize Maintenance Problems: Maintenance work management process begins with work identification, which is identifying work that needs to be performed .
2. Inspection and Reporting of Faults: One of the important forms of maintenance is to inspect at the right time and duly record the data to produce an inspection report .
3. Maintenance Resources Allocation: The resources needed for maintenance consist of human resources, capital, tools, and information and the quality of human resources will depend on the environment of the company .
4. Continuous Improvement: Continuous improvement is best described as constantly striving for better ways to do things and comparing one's operation to others to find better ways to the functional reliability of an item .
5. Maintenance Quality Supervision: Proper maintenance quality supervision provides recording data of executed maintenance works, availing all the necessary resources at the right time .
6. Measure maintenance performance: Maintenance performance can be properly managed in a well-planned manner effectively and efficiently to make the road safe, serviceable, and stable .
2.6. Maintenance Management Controlling
Maintenance controlling is defined as the performance measurement system with indicators that are able to measure important elements of maintenance functions performance .
1. Inventory Control: Maintenance inventory control is an important maintenance management practice used to show how much inventory you have at any one time and how to keep track of it in a maintenance organization .
2. Financial Control: Financial Control deals with the fiscal control procedures of the maintenance organization .
3. Maintenance Task Execution: Maintenance task execution ensures the scheduled activities are carried out within the allocated time and through the effective use of resources .
3. Study Methodology
The main purpose of this research is to construct an evaluation model for the pavement maintenance management practice in the Ethiopian road authority. The factor analysis and FAHP methods are used in a two-stage process. In the first stage: factor analysis was employed to reduce a huge number of inter-correlated measures to a few representative constructs . In the second stage, the underlying structure of items in a data set was used as criteria weights in fuzzy AHP, and the fuzzy preference weights of the hierarchy were calculated using the matrix constructed by FAHP.
3.1. Data Collection
Figure 1. The steps, and procedures conducted by the applied methodologies. Source: own work, 2023.
The necessary data for this study was first obtained from the recent literature review regarding the concept of the pavement maintenance management practice. To reduce the number of items in a questionnaire for identifying the underlying structure of items in a data set factor analysis was performed and sixty-one questionnaires were distributed to the staff members of pavement maintenance management professionals and academicians in the Ethiopian road authority, and the number of valid questionnaires is sixty-one. In the case of fuzzy AHP, fifteen senior decision experts were selected from academicians and industrialists in the maintenance of roads. To measure the internal consistency or reliability of the questionnaire Cronbach’s alpha, and consistency ratio methods were applied. The steps and procedures of the applied technique are presented in the following sub-sections.
3.2 Factor Analysis
Factor analysis can be applied to developing a questionnaire. In doing the analysis, irrelevant questions can be removed from the final questionnaire . Factor Model with ‘m’ Common Factors Let X=(X1, X2, .Xp)’ is a random vector with mean vector μ and covariance matrix Σ . The factor analysis model assumes that = μ + λ F + ε, where,  λ={λjk}n*m the matrix of factor loadings; λjk is the loading of the jth variable on the kth common factor, F=(F1, F2, .Fm)’ denotes the vector of latent factor scores; Fk is the score on the kth common factor and ε =(ε 1, ε 2, .ε p)’ denotes the vector of latent error terms; ε j is the jth specific factor .
There are three major steps involved in factor analysis: i) assessment of the suitability of the data, ii) factor extraction, and iii) factor rotation and interpretation. They are described as :
3.2.1. Assessment of the Suitability of the Data
To determine the suitability of the data set for factor analysis, sample size and strength of the relationship among the items have to be considered . Generally, a larger sample is recommended for factor analysis. Nevertheless, a smaller sample size can also be sufficient if solutions have several high-loading marker variables < 0.80 .
Determinant Score
The value of the determinant is an important test for multicollinearity or singularity. The determinant score of the correlation matrix should be > 0.00001 which specifies that there is an absence of multicollinearity.
1) Kaiser-Meyer-Olkin (KMO) Measure of Sampling Adequacy
The KMO test is a measure that has been intended to measure the suitability of data for factor analysis. The KMO measure of sampling adequacy is given by the formula :
KMOi=ijRij2ijRij2+ijUij2(1)
2) Bartlett’s Test of Sphericity
The significant value < 0.05 indicates that a factor analysis may be worthwhile for the data set. To measure the overall relation between the variables the determinant of the correlation matrix R is calculated. Under H0, R =1; if the variables are highly correlated, then R ≈ 0. The Bartlett’s test of Sphericity is given by :
x2=-n-1-2p+56*lnR(2)
Where, p= number of variables, n= total sample size and R= correlation matrix
3.2.2. Factor Extraction
Factor extraction encompasses determining the least number of factors that can be used to best represent the interrelationships among the set of variables :
1) Kaiser’s (Eigenvalue) Criterion
The eigenvalue of a factor represents the amount of the total variance explained by that factor. In factor analysis, the remarkable factors having eigenvalue greater than one are retained and considered to be significant .
2) Scree Test
A scree plot graphs eigenvalue magnitudes on the vertical access, with eigenvalue numbers constituting the horizontal axis .
3.2.3. Factor Rotation and Interpretation
There are two main approaches to factor rotation; orthogonal (uncorrelated) or oblique (correlated) factor solutions. In this study, orthogonal factor rotation is used because it results in solutions that are easier to interpret and report .
1) Orthogonal Factor Model Assumptions
The orthogonal factor analysis model assumes the form X = μ + λ F + ε, and adds the assumption that F~ 0, 1m (i.e. the latent factors have mean zero, unit variance, and are uncorrelated, Ε ~ (0, Ψ) where Ψ = diag(Ψ1, Ψ2,Ψn with Ψi denoting the jth specific variance, ε j, and Fk, are independent of one another for all pairs, j, k.
2) Variance Explained by Common Factors
The portion of the variance of the jth the variable that is explained by the ‘m’ common factors is called the communality of the jth variable:σ jj=hj2+Ψj where, σ jj is the variance of j (i.e. jth diagonal of Σ). Communality is the sum of squared loadings for j and given by hj2=(λλ) jj=λ  j12+ λ  j22+......+ λ  jm2 is the communality of Xj, and Ψj is the specific variance (or uniqueness) of  Xj.
3.3. Fuzzy AHP and Fuzzy Set Theory
The Fuzzy AHP extends this framework by incorporating the use of fuzzy logic, which enables comparisons between elements that are not easily quantifiable . Fuzzy Set Theory is used to model the subjective and uncertain aspects of the problem. These membership functions can be defined based on linguistic terms provided by decision-makers, such as "absolutely preferred " or " not preferred ". A fuzzy set A={(x,μA(x))/xϵX}, is a set of ordered pairs and X is a subset of the real numbers R, where μA(x) is called the membership function which assigns to each object "x" a grade of membership ranging from zero to one . If the membership value is 1, it is the full element of the set; if it is 0, it is not the element of the set. In contrast to classical sets, the membership degrees of the elements can vary in infinite numbers between the range of [0, 1] in fuzzy sets .
1) Membership Function
The membership function of à fuzzy set is shown by μÃ(x). Fuzzy sets described each object with the membership function having a degree of membership ranging between 0 and 1 . If x element belongs to à fuzzy set, it is μÃ(x) =1; if it does not belong to, it is μÃ(x) =0 . In the current study, the triangular membership function is used .
2) Verbal /linguistic variables
In fuzzy logic, verbal/linguistic variables are an important concept of fuzzy sets. Linguistic variables are used to express human feelings and decisions .
3) Fuzzy numbers
Fuzzy numbers are a fuzzy subset of real numbers. Fuzzy numbers are used to handle the indefinite numerical values such as around 7 or close to 10 . The TFN is determined by three real numbers consisting of "M" = {l, m, u}. The parameters l, m, and u signify the smallest possible value, the most promising value, and the largest value of fuzzy event .
The membership function of a triangular fuzzy number (TFN) 𝐴, is a function μA(x): R → [0, 1], defined as .
µ̃(x) =0, x<l x-l/m-l, lxmu-x/u-m, mxu 0, x>u (3)
Where, inequality 𝑙 ≤ 𝑚 ≤ 𝑢 holds, Variables 𝑙, 𝑚, and 𝑢 are the lower, middle, and upper values, respectively, and when 𝑙 = 𝑚 = 𝑢, TFN becomes a crisp number.
Figure 2. The membership function of the triangular fuzzy number .
The TFN can be denoted by Ã=(l, m,u). Assume two TFNs, ̃1= (l1, m1, u1) and  A ̃2= (l2, m2, u2) and scalar 𝑘 > 0, 𝑘 ∈ R. The basic arithmetic operations are defined as follows .
Addition of the fuzzy number ⊕.
Ã1Ã2= (l1+l2,m1+m2,u1+u2)(4)
Multiplication of the fuzzy number ⊗ .
Ã1Ã2= (l1*l2,m1*m2,u1*u2), forl1,l2> 0;m1,m2> 0;u1,u2> 0 (5)
Subtraction of the fuzzy number Ɵ .
Ã1ƟÃ2= (l1–l2,m1-m2,u1-u2)(6)
Division of a fuzzy number .
Ã1Ã2= (l1/m2,m1/m2,u1/l2), forl1,l2> 0;m1,m2> 0;u1,u2> 0 (7)
Reciprocal of the fuzzy number .
Ã-1 = (l1, m1, u1))-1= (1/u1,1/m1, 1/ l1), for l1,l2> 0; m1, m2> 0; u1, u2> 0 (8)
The following steps were used to implement the fuzzy AHP technique .
3.3.1. Structuring the Hierarchical Decision-making Problem
In the first step, the hierarchical decision-making problem is structured. The structures of the analytic hierarchy process were established by identifying six variable groups and their associated sub-criteria (a total of 30 variables).
3.3.2. Develop a Pair-wise Fuzzy Comparison Matrix
As in the conventional AHP, n(n-1)/2 K, experts (decision-makers) are required for each comparison group for a level to construct a positive fuzzy reciprocal comparison matrix Ă = {ãij}. The matrix is expressed as follows .
Ã= {ãij} =1 ã12.ã1nã211.ã2nã31ã32.a3n....ãn1ãn21 =1ã12...ã1n1ã121.ã2n1ã131ã23ã3n......1ã1n1ã2n..1(9)
Where,ãij=1̃,3̃,5̃,7̃,9̃ The variable i is relative preferred to variable j1 i=j Variable i is equally preferred to variable j1̃-1,3̃-1,5̃-1,7̃-1,9̃-1 The variable i is relatively less preferred than variable j
Table 1. Linguistic terms and the corresponding triangular fuzzy numbers .

Saaty scale

Linguistic Variable

Fuzzy Number

Triangular Fuzzy Scale

Reverse Triangular Fuzzy Number

1

Equally preferred (EP)

1̃

(1, 1, 3)

13, 11, 11

3

Moderate preferred (MP)

3̃

(1, 3, 5)

15, 13, 11

5

Strong preferred (SP)

5̃

(3, 5, 7)

17, 15, 13

7

Very strong preferred (VSP)

7̃

(5, 7, 9)

19, 17, 15

9

Absolute preferred (AP)

9̃

(7, 9, 9)

19, 19, 17

2, 4, 6, 8, are intermediate values between the two adjacent judgments

Figure 3. Linguistic variables for the importance weight of each criterion .
Once the number of the decision of the experts were determined and the experts were then asked to perform pair-wise comparisons between the dimension and the compared dimension .
Table 2. Linguistic variables describing weights of the criteria and values of ratings .

Linguistic Variable

Fuzzy numbers

Membership function

Domain

Triangular Fuzzy Scale (l, m, u)

Just equal

1̃

1

1

(1, 1, 1)

Equally preferred

µ(A)(x) = (3-x) / (3-1)

1 ≤ x ≤ 3

(1, 1, 3)

Moderately preferred

3̃

µ(A)(x) = (x-1) / (3-1)

1 ≤ x ≤ 3

(1, 3, 5)

µ(A)(x) = (5-x) / (5-3)

3 ≤ x ≤ 5

Strongly preferred

5̃

µ(A)(x) = (x-3) / (5-3)

3 ≤ x ≤ 5

(3, 5, 7)

µ(A)(x) = (7-x) / (7-5)

5 ≤ x ≤ 7

Very strongly preferred

7̃

µ(A)(x) = (x-5) / (7-5)

5 ≤ x ≤ 7

(5, 7, 9)

µ(A)(x) = (9-x) / (9-7)

7 ≤ x ≤ 9

Absolutely preferred

9̃

µ(A)(x) = (x-7) / (9-7)

7 ≤ x ≤ 9

(7, 9, 9)

3.3.3. Test Hierarchy Consistency
AHP develops a consistency measure, by using a consistency ratio that is calculated using the consistency index, CI, and random index, RI .
CI=λmax-nn-1 (10)
Where λmax the maximum eigenvalue and n is is the dimension of the judgment matrix.
RI is obtained by averaging the CI of a randomly generated reciprocal matrix, and N is the number of items compared.
Table 3. Random consistency index .

Matrix Dimension

1

2

3

4

5

6

7

8

9

10

RI

0

0

0.58

0.90

1.12

1.24

1.32

1.41

1.45

1.49

If CR, the ratio of CI and RI is less than 10%, then the evaluations of the decision maker can be considered as having an acceptable consistency, the calculated consistency ration should be less than or equal to 0.1.
CR=CIRI (11)
Where CR is the consistency ratio RI is the random index.
3.3.4. Weights Aggregations
If there is more than one decision maker, the preferences of each decision maker of alternatives, and the final priorities of the alternatives can be obtained by aggregating the local priorities of elements of different levels, which are obtained in the above steps .
ãij= (ãij1ãij2ãij3… ….⊗ãijN)1/n(12)
Where, ãij - is the integrated triangle fuzzy number by N experts.
ãijk - is the i-th to the j-th variable pair comparison by expert k.
⊗ - is the symbol of matrix multiplication.
3.3.5. Calculate Geometric Mean of Triangular Fuzzy Numbers
The geometric mean of the triangular fuzzy numbers values of each criterion is calculated as shown in Eq. (13). Here r̃i still represents triangular values .
r̃i= (ãi1ãi2ãi3⊗….⊗ãin)1/n(13)
3.3.6. Calculate the Fuzzy Weight of Variables
To find the fuzzy weight of criterion i (w̃i), multiply each r̃i with this reverse vector.
w̃i=r̃i⊗(r̃1r̃2r̃3⊕………⊕r̃n)-1(14)
Where ãin is the fuzzy comparison value of variable i to variable n.
r̃i is the geometric mean of the fuzzy comparison value of variable i to each variable,
w̃i is the fuzzy weight of the i-th variables, which can be indicated by a triangular fuzzy number.
⊕ is the symbol of matrix plus.
3.3.7. Defuzzification
The defuzzification phase starts with the weighted vector w̃i, since w̃i are still fuzzy triangular numbers they need to be de-fuzzified to obtain the total integral value for the TFNs by the center of area method , via applying Eq. (15).
BNPi = [(Uwi - Lwi) + (Mwi - Lwi)]3+Lwi(15)
3.3.8. Normalize Weights to Make Sure the Sum of Weights Add-up to 1
Remember the sum of factors must add-up to one. In normalization, normalized vectors 𝑤𝑖 for criteria are obtained .
BNPw1 = BNP1(BNP1 + BNP2 . + BNPn) (16)
3.3.9. Ranking
The weights for each sub-criterion are obtained by multiplying the weights of the criteria and sub-criteria. Then, arranging the obtained weights, the sub-criteria ranking is received .
4. Data Analysis
4.1. Factor Analysis Results
In carrying the results, the data was analyzed by using the statistical software SPSS. This study has followed three major steps for factor analysis: a) assessment of the suitability of the data, b) factor extraction, and c) factor rotation and interpretation.
4.1.1. Step 1: Assessment of the Suitability of the Data
To analyze the pavement maintenance management practice, Kaiser-Meyer-Olkin is used to measure the suitability of data for factor analysis. The correlation matrix shows that there are a few items whose inter-correlations > 0.3 between the variables. The value for the determinant is an important test for multi-collinearity.
Table 4. Factor Correlation Matrix. Source: own work, 2022.

Component

1

2

3

4

5

6

Correlation

1

1.000

2

.125

1.000

3

-.003

.248

1.000

4

.180

.334

.125

1.000

5

.320

.368

.343

.156

1.000

6

.074

.383

.275

.171

.320

1.000

Extraction Method: Principal Axis Factoring.
Rotation Method: Promax with Kaiser Normalization.
Table 5 illustrates the value of KMO statistics is equal to 0.709 > 0.6 which indicates that sampling is adequate. Bartlett’s test of Sphericity is highly significant at p < 0.001 which shows that the correlation matrix has significant correlations among at least some of the variables.
Table 5. Kaiser-Meyer-Olkin and Bartlett’s Test of Sphericity.

KMO and Bartlett's Test

Kaiser-Meyer-Olkin Measure of Sampling Adequacy.

0.709

Bartlett's Test of Sphericity

Approx. Chi-Square

53.326

Df

19

Sig.

.000

4.1.2. Step 2: Factor Extraction
Table 6 demonstrates the eigenvalues and total variance explained. The result shows that 78.90% common variance shared by thirty variables can be accounted for by six variables.
Table 6. Eigenvalues (EV) and Total Variance Explained.

Total Variance Explained

Component

Initial Eigenvalues

Extraction Sums of Squared Loadings

Rotation Sums of Squared Loadings

Total

% of Variance

Cumulative%

Total

% of Variance

Cumulative%

Total

% of Variance

Cumulative%

1

7.890

26.299

26.299

7.890

26.299

26.299

5.045

16.816

16.816

2

4.938

16.459

42.759

4.938

16.459

42.759

4.226

14.086

30.902

3

3.270

10.900

53.658

3.270

10.900

53.658

4.066

13.554

44.455

4

2.605

8.682

62.341

2.605

8.682

62.341

3.467

11.558

56.013

5

2.101

7.004

69.344

2.101

7.004

69.344

3.125

10.418

66.431

6

1.802

6.007

75.352

1.802

6.007

75.352

2.676

8.921

75.352

Extraction Method: Principal Component Analysis.

Figure 4. Scree Plot of Factor Analysis.
In Figure 4, for the Scree test, a graph is plotted with eigenvalues on the y-axis against the six component numbers in their order of extraction on the x-axis. The initial factors extracted are large factors with higher eigenvalues followed by smaller factors.
4.1.3. Step 3: Factor Rotation and Interpretation
The present study has executed the extraction method based on principal component analysis and the orthogonal rotation method based on varimax with Kaiser Normalization. The communalities reflect the common variance in the data structure after the extraction of factors/variables.
Table 7. The items/factor structure of the pavement maintenance management practice in the Ethiopian roads authority after variable reduction procedures.

Rotated Component Matrix

Component

1

2

3

4

5

6

Cooperation and coordination of the maintenance team

0.734

Maintenance Management Team leader

0.827

A commitment of the Maintenance Management Team

0.827

Maintenance leadership

0.768

Maintenance Management Team meetings

0.686

Private Contractor Participation for Maintenance

0.786

Staffing skilled manpower

0.796

Maintenance Management Team Capacity and Capability

0.762

Written Maintenance Management Plan

0.715

Strategic Maintenance Plan

0.785

Staff Involvement in Developing the Maintenance Plan

0.812

Maintenance Management Plan Revision

0.799

Budget for Financing Maintenance Programs

0.715

Routine maintenance

0.818

Periodic maintenance

0.879

Emergency maintenance

0.826

Preventive maintenance

0.932

Corrective maintenance

0.904

Maintenance checklists

0.662

Maintenance Staff Training

0.945

Schedule maintenance work

0.947

Documentation and Recordkeeping

0.792

Identify and categorize maintenance problems

0.77

Inspection and reporting of faults

0.879

Maintenance Resources allocation

0.846

Quality supervision

0.879

Measure maintenance performance

0.782

Inventory Control

0.725

Financial Control

0.92

Maintenance Task Execution

0.907

Extraction Method: Principal Component Analysis.

Rotation Method: Varimax with Kaiser Normalization.

a. Rotation converged in 6 iterations.

4.1.4. Reliability Analysis
The reliability of a questionnaire is examined with Cronbach’s alpha. It provides a simple way to measure whether or not a score is reliable .
α= nr̅(1+r̅(n-1))(17)
The Cronbach’s alpha coefficient for the factors/variables with total scale reliability is 0.898 > 0.7. It shows that the variables exhibit a correlation with their component grouping and thus they are internally consistent.
Table 8. Reliability Results.

Constructs

Reliability (Cronbach's Alpha)

Number of items

Component 1

0.910

8

Component 2

0.868

5

Component 3

0.938

5

Component 4

0.881

4

Component 5

0.929

5

Component 6

0.882

3

Total scale reliability

0.898

30

4.2. Fuzzy Analytic Hierarchy Process Results
After conducting the factor analysis for identifying the underlying factors/variables, and the number of variables/ factors to retain in the factor loading matrix, it was further analyzed by using the FAHP methodologies for prioritizing, and ranking of the identified pavement maintenance management practice which was conducted in the Ethiopian road authority. The following steps were implemented for conducting the fuzzy AHP technique.
4.2.1. Structuring the Hierarchical Decision
In this study, a hierarchical structure was established in the e first step in the AHP and then the questionnaire was designed. There is a total of 30 evaluation criteria categorized into six main dimensions shown in Figure 5. The hierarchical structure presented in three levels in which the goal of the decision was presented in the top, the six variable groups and thirty criteria are located in the second and third levels, respectively in the form of a hierarchical diagram.
4.2.2. Develop a Pair-wise Fuzzy Comparison Matrix
The use of ratings enables DMs to analyze each criterion concerning other criteria for their subsequent ranking relative to each other. A decision matrix ‘D’ as shown in Table 9 may be constructed to measure the relative degree of importance for each success factor or criteria, based on the proposed methodology.
Table 9. Fuzzy pairwise comparison matrix of criteria concerning the overall objective.

D

C1

C2

C3

C4

C5

C6

C1

(1,1,1)

(2,3,4)

(3,4,5)

(2,3,4)

(4,5,6)

(2,3,4)

C2

(1/4,1/3,1/2)

(1,1,1)

(1/3,1/2,1)

(1/5,1/4,1/3)

(2,3,4)

(3,4,5)

C3

(1/5,1/4,1/3)

(1,2,3)

(1,1,1)

(1/3,1/2,1)

(3,4,5)

(1/3,1/2,1)

C4

(1/4,1/3,1/2)

(3,4,5)

(1,2,3)

(1,1,1)

(4,5,6)

(2,3,4)

C5

(1/6,1/5,4)

(1/4,1/3,1/2)

(1/5,1/4,1/3)

(1/6,1/5,1/4)

(1,1,1)

(1/5,1/4,1/3)

C6

(1/4,1/3,1/2)

(1/5,1/4,1/3)

(1,2,3)

(1/4,1/3,1/2)

(3,4,5)

(1,1,1)

Figure 5. The proposed multi-criteria decision-making model for pavement maintenance management practice.
4.2.3. Test Hierarchy Consistency
The Eigenvalue method was suggested to perform the consistency check. The consistency ratio (CR) was defined as a ratio between the consistency of a given evaluation matrix and the consistency of a random matrix where RI is a random index that depends on n, as shown in Table 3. The Eigenvalue method was used to perform a consistency check by finding the value of λmax. Then, the consistency index (CI) and consistency ratio (CR) can be done by using Eq. (10) and Eq. (11).
CI=λmax-nn-1=CI=6.091 -66-1=0.018
CI=0.018, λmax= 6.091,n= 6, RI(n=6)=1.24.
CR= 0.0181.24 =0.014 < 0.1
Therefore, the pairwise comparison matrix is acceptable. Similarly, the consistency ratios of all other conducted and the results are less than 10%. Thus, all the judgments are acceptable consistency.
4.2.4. Weights Aggregations
After checking the validation of the expert’s opinion, the geometric mean method aggregates the preference of the overall decision experts in relation to the objective with a triangular fuzzy number by using Eq. (12).
ãij= (ãij1ãij2ãij3… ….⊗ãijN)1/15
As a sample calculation, the aggregated fuzzy pairwise comparison values for the criteria with respect to the goal are shown in in Table 10.
Table 10. The aggregated fuzzy pairwise comparison values for the criteria with respect to the goal.

V1

V2

V3

V4

V5

V6

V1

1.000, 1.000, 1.000

0.384, 1.103, 2.656

0.569, 1.179, 2.428

0.834, 1.534, 2.945

2.378, 3.965, 6.010

2.070, 3.415, 5.152

V2

0.376, 0.907, 2.605

1.000, 1.000, 1.000

0.681, 1.397, 2.789

0.999, 1.865, 3.317

1.858, 3.174, 5.052

1.513, 2.578, 4.179

V3

0.441, 0.883, 1.809

0.344, 0.658, 1.370

1.000, 1.000, 1.000

0.486, 1.297, 3.442

2.380, 4.407, 7.671

2.021, 3.837, 7.157

V4

0.340, 0.652, 1.199

0.286, 0.500, 0.897

0.291, 0.771, 2.059

1.000, 1.000, 1.000

1.661, 3.754, 7.834

1.780, 4.161, 9. 202

V5

0.166, 0.252, 0.420

0.198, 0.315, 0.538

0.130, 0.227, 0.420

0.125, 0.259, 0.578

1.000, 1.000, 1.000

1.446, 3.223, 6.820

V6

0.199, 0.296, 0.483

0.254, 0.404, 0.678

0.153, 0.279, 0.523

0.130, 0.272, 0.620

0.147, 0.310, 0.692

1.000, 1.000, 1.000

4.2.5. Geometric Mean Calculation of Triangular Fuzzy Numbers
The geometric mean of the fuzzy comparison values was found using the FAHP and Microsoft Excel for each criterion. Using Eq. (13), the geometric mean for criteria 1 was calculated as follows:
r̃1 = ((1 ⊗ 0.384 ⊗ 0.569 ⊗ 0.834 ⊗ 2.378 ⊗ 2.070) 1/6, (1 ⊗ 1.103 ⊗ 1.179 ⊗ 1.534 ⊗ 3.965 ⊗ 3.415) 1/6, (1 ⊗ 2.656 ⊗ 2.428 ⊗ 2.945 ⊗ 6.010 ⊗ 5.152) 1/6
r̃1 = (0.870, 1.412, 2.202)
With similar steps, other calculations of the geometric means of fuzzy comparison values for each criterion are determined. It also includes the total values, the inverse values, and the values in increasing order. r̃2 = (0.884, 1.399, 2.226)
r̃3 = (0.748, 1.221, 2.007)
r̃4 = (0.601, 0.990, 1.609)
r̃5 = (0.285, 0.409, 0.617)
r̃6 = (0.230, 0.376, 0.647)
Fuzzy Weight Calculation
The fuzzy preference weights are calculated, and the results are presented below after fuzzy weights for each criterion were computed using Eq. (14) as follows:
w̃1 = r̃1 ⊗ (r̃1r̃2r̃3 r̃4r̃5 r̃6)-1
Where, r̃i was multiplied by the inverse of the summation vector in the form of increasing order.
w̃1 = (0.870, 1.412, 2.202) ⊗ 12.202+. + 0.647, 11.412++ 0.376, 10.870+. +0.230
w̃1 = (0.093, 0.243, 0.609)
Likewise, the residual fuzzy weights w̃i values are:
w̃2 = 0.095, 0.241, 0.615
w̃3 = 0.080, 0.210, 0.555
w̃4 = 0.065, 0.171, 0.445
w̃5 = 0.031, 0.070, 0.170
w̃6 = 0.025, 0.065, 0.179
Table 11. The fuzzy weights of the variables.

Decision Variables

Fuzzy Weights(w̃i)

BNP

Normalized Local weights (BNPw)

Rank

Fuzzy weights of the variable groups (Vi) with respect to the goal

Maintenance Management Team

0.093

0.243

0.609

0.315

0.256

2

Maintenance Management Plan

0.095

0.241

0.615

0.317

0.258

1

Maintenance Approaches

0.08

0.21

0.555

0.282

0.229

3

Maintenance Information and Communication management

0.065

0.171

0.445

0.227

0.184

4

Maintenance Identification and Assessment

0.031

0.07

0.17

0.09

0.073

5

Maintenance Controlling Management

0.025

0.065

0.179

0.089

0.073

6

Fuzzy weights of the sub-criteria under C1 (Cij): Maintenance Management Team

Cooperation and coordination of the maintenance team

0.07

0.118

0.206

0.131

0.119

4

Maintenance Management Team leader

0.158

0.277

0.461

0.299

0.271

1

A commitment of the Maintenance Management Team

0.038

0.064

0.113

0.072

0.065

7

Maintenance leadership

0.073

0.125

0.215

0.138

0.125

3

Maintenance Management Team meetings

0.038

0.064

0.111

0.071

0.065

8

Private Contractor Participation for Maintenance

0.083

0.143

0.249

0.158

0.144

2

Staffing skilled manpower

0.059

0.102

0.176

0.112

0.102

6

Maintenance Management Team Capacity and Capability

0.063

0.108

0.187

0.119

0.109

5

Fuzzy weights of the sub-criteria under C2 (Cij): Maintenance Management Plan

Written Maintenance Management Plan

0.165

0.278

0.465

0.303

0.277

1

Strategic Maintenance Plan

0.125

0.212

0.36

0.232

0.212

3

Staff Involvement in Developing the Maintenance Plan

0.137

0.236

0.405

0.259

0.237

2

Maintenance Management Plan Revision

0.075

0.124

0.211

0.137

0.125

5

Budget for Financing Maintenance Programs

0.089

0.147

0.242

0.159

0.146

4

Fuzzy weights of the sub-criteria under C3 (Cij): Maintenance Approaches

Periodic maintenance

0.165

0.278

0.466

0.303

0.277

1

Preventive maintenance

0.125

0.212

0.36

0.233

0.213

3

Routine maintenance

0.138

0.237

0.405

0.26

0.238

2

Emergency maintenance

0.076

0.125

0.211

0.137

0.126

5

Corrective maintenance

0.089

0.148

0.242

0.16

0.146

4

Fuzzy weights of the sub-criteria under C4 (Cij): Maintenance Information and Communication Management

Maintenance checklists

0.25

0.368

0.545

0.388

0.37

2

Maintenance Staff Training

0.271

0.391

0.553

0.405

0.386

1

Schedule maintenance work

0.073

0.106

0.156

0.112

0.107

4

Documentation and Recordkeeping

0.093

0.134

0.202

0.143

0.137

3

Fuzzy weights of the sub-criteria under C5 (Cij): Maintenance Identification and Assessment

Identify and categorize maintenance problems

0.15

0.26

0.438

0.283

0.258

1

Inspection and reporting of faults

0.114

0.195

0.34

0.216

0.197

4

Maintenance Resources allocation

0.13

0.22

0.381

0.244

0.222

2

Quality supervision

0.129

0.221

0.372

0.241

0.219

3

Measure maintenance performance

0.064

0.103

0.172

0.113

0.103

5

Fuzzy weights of the sub-criteria under C6 (Cij): Maintenance Controlling Management

Inventory Control

0.522

0.639

0.779

0.647

0.638

1

Financial Control

0.127

0.158

0.2

0.162

0.16

3

Maintenance Task Execution

0.163

0.202

0.251

0.206

0.203

2

4.2.6. Defuzzification
The average of the fuzzy values for each criterion, which was based on Eq. (15), was used to determine the relative non-fuzzy weight or defuzzified weight of each criterion. The calculation of defuzzification was as follows.
BNPi = [(Uwi - Lwi) + (Mwi - Lwi)]3+Lwi
BNP= [(0.609 - 0.093) + (0.243 - 0.093)]/3 + 0.093
BNP= 0.315
4.2.7. Normalizing the Defuzzified Weight of Criterion
Then, the defuzzified weights must be normalized using Eq. (16) along with the normalized weights for each criterion. Therefore, the normalization weight of C1 can be calculated as follows:
BNPw1 = BNP1(BNP1 + BNP2 . + BNPn) 
BNPw1 = 0.315/ (0.315 + 0.317 + 0.282 + 0.227+ 0.090 + 0.089) = 0.256
Table 12. Weighted values and rankings considered by decision experts.

Dimension

Local Weight

Sub criteria (Cij)

Local Weights

Global Weights

Ranking by Category

Overall Ranking

Maintenance Management Team

0.256

Cooperation and coordination of the maintenance team

0.119

0.030

24

16

Maintenance Management Team leader

0.271

0.069

6

3

A commitment of the Maintenance Management Team

0.065

0.017

29

23

Maintenance leadership

0.125

0.032

23

15

Maintenance Management Team meetings

0.065

0.017

29

23

Private Contractor Participation for Maintenance

0.144

0.037

19

12

Staffing skilled manpower

0.102

0.026

28

19

Maintenance Management Team Capacity and Capability

0.109

0.028

25

18

Maintenance Management Plan

0.258

Written Maintenance Management Plan

0.278

0.072

4

1

Strategic Maintenance Plan

0.213

0.055

13

7

Staff Involvement in Developing the Maintenance Plan

0.238

0.061

9

6

Maintenance Management Plan Revision

0.126

0.032

22

14

Budget for Financing Maintenance Programs

0.146

0.038

17

11

Maintenance Approaches

0.229

Periodic maintenance

0.277

0.063

5

5

Preventive maintenance

0.213

0.049

12

9

Routine maintenance

0.238

0.055

8

8

Emergency maintenance

0.126

0.029

21

17

Corrective maintenance

0.146

0.033

18

13

Maintenance Information and Communication management

0.184

Maintenance checklists

0.370

0.068

3

4

Maintenance Staff Training

0.386

0.071

2

2

Schedule maintenance work

0.107

0.020

26

21

Documentation and Recordkeeping

0.137

0.025

20

20

Economic condition

0.073

Identify and categorize maintenance problems

0.258

0.019

7

22

Inspection and reporting of faults

0.197

0.014

15

28

Maintenance Resources allocation

0.222

0.016

10

25

Quality supervision

0.219

0.016

11

26

Measure maintenance performance

0.103

0.008

27

30

Maintenance Identification and Assessment

0.073

Inventory Control

0.638

0.047

1

10

Financial Control

0.160

0.012

16

29

Maintenance Task Execution

0.203

0.015

14

27

Similarly, the BNP value of the remaining dimension and sub-criteria can be obtained in a similar computational procedure (see Table 11). The normalized weights of criteria placed at the third level in the hierarchy can be presented in Table 12.
5. Discussion of Research Results, and Implications
These studies evaluate the pavement maintenance management practice in the Ethiopian roads authority by integrating factor analysis and fuzzy AHP methods. As it was observed in Table 12, the decision experts compared local weights in each group variable and ranked maintenance management plan (0.258), and maintenance management team (0.256) as the first and second most maintenance management practice in the pavement. Thus, the decision experts believe that the maintenance management plan and maintenance management team have been exercised by the maintenance staff in their company. Maintenance Approaches (0.229) is the next maintenance management practice in the pavement identified by the decision experts followed by maintenance information and communication management (0.184), and Maintenance Identification and Assessment (0.073). Contrariwise, Maintenance Controlling Management (0.073) is poorly practiced in the management of pavement maintenance.
The results indicate that the decision experts are convinced that the maintenance practice like maintenance management plan and maintenance management team overshadow the practice in the Ethiopian Roads Authority. Hence, the maintenance staff in the Ethiopian Roads Authority should be taken into consideration and put in more effort and attention to improve those maintenance management practices.
Individually, further examining each sub-criteria under their dimension, the greatest weighted value under the maintenance management team category was Maintenance Management Team leader (0.299), Private Contractor Participation for Maintenance (0.158), Maintenance leadership (0.138), Cooperation and coordination of maintenance team (0.131), and Maintenance Management Team capacity and capability (0.119). On the contrary staffing skilled manpower (0.112), commitment of maintenance management team (0.072), and maintenance management team meetings (0.071).
Next, the Written Maintenance Management Plan (0.3033), Staff Involvement in Developing the Maintenance Plan (0.259), and Strategic Maintenance Plan (0.232) maintenance management practice, were identified as the most practiced by the Ethiopian roads authority. Contrariwise, the Budget for Financing Maintenance Programs (0.159), and Maintenance Management Plan Revision (0.137) were poorly practiced by the Ethiopian Roads Authority.
Furthermore, the highest most practiced sub-criteria under the maintenance approaches were Periodic maintenance (0.303), Routine maintenance (0.260), and Preventive maintenance (0.233). Contrariwise, Corrective maintenance (0.160), and Emergency maintenance (0.137) were poorly practiced management approaches in pavement maintenance.
This finding can be supported by , that periodic maintenance management was considered the best road maintenance management approach by the Ethiopian Roads Authority. The operation is occasionally required on a section of road after a period of a number of years. He also proved that periodic maintenance is based on a detailed inspection performed at certain time intervals such as seasonally or yearly depending on the type and kind of facilities.
Moreover, the maintenance management practice which is mostly practiced in the Ethiopian road authority under the maintenance information and communication management category were Maintenance Staff Training (0.405), Maintenance checklists (0.388), and Documentation and Recordkeeping (0.143). Contrariwise, Schedule maintenance work (0.112) was poorly practiced pavement maintenance management practice.
Additionally, the greatest weighted values under the maintenance identification and assessment category were Identified and categorized as maintenance problems (0.283), Maintenance Resources allocation (0.244), and Quality supervision (0.241).
On the contrary, Inspection and reporting of faults (0.216) and Measure maintenance performance (0.113) were poorly practiced pavement maintenance management practices.
Finally, the results revealed that Inventory Control (0.647), and Maintenance Task Execution (0.206) were identified as the best pavement maintenance management practice under maintenance controlling management maintenance practice. Contrariwise, Financial Control (0.162) was identified as poorly practiced pavement maintenance management practices by the Ethiopian Roads Authority.
Overall, the sub-criteria with the highest-ranked final weights among global weights were written maintenance management plan (0.072), maintenance staff training (0.071), maintenance management team leader (0.069), maintenance checklists (0.068), and periodic maintenance (0.063).
The implication is that the level of awareness of the highest-ranked pavement maintenance management practice is good, thus, there is a need to upkeep those maintenance practices. So, it needs attention to advance those maintenance management practices in the Ethiopian roads authority to achieve the goal of the company.
On the contrary, quality supervision (0.016), maintenance task execution (0.015), inspection and reporting of faults (0.014), financial control (0.012), and measure maintenance performance (0.008) were identified as poorly practiced pavement management practice in the Ethiopian roads authority. Hence, the maintenance staff in the Ethiopian Roads Authority ought to take into consideration and put in more effort and attention to improve those maintenance management practices while handling managing maintenance.
The implication is that the level of awareness on the above-identified pavement maintenance management practice is poor, thus, there is a need to intensify those maintenance management practices in the Ethiopian roads authority. It also indicates that the maintenance practices were taking place when the staff failed to carry out the maintenance practices regularly based on the standards of the practice. Thus, the maintenance staff should consider those and put in more effort and attention to advance the maintenance management practices.
This study provides knowledgeable in view of the pavement maintenance management practice in the Ethiopian roads authority by integrating factor analysis and fuzzy AHP methods. It can also help us to comprehend how academicians carry out a study by using a comprehensive model. This study helps us important implications for the practitioners, and project managers to have a clear understanding of the pavement maintenance management practice that is improperly adopted on the roads. The findings of this study provide academia and practitioners with insightful information to enhance the current pavement maintenance management practice and help us to take proactive measures and get the optimum result for poorly practiced pavement maintenance.
6. Conclusions
Based on the findings and discussion of the study the following conclusions are suggested:
1. Pavement maintenance management practices were extracted through performing exploratory factor analysis on thirty items developed from a synthesis of the literature and perception of practitioners in the construction sector.
2. The extracted pavement maintenance management practice was further analyzed via the fuzzy AHP model to prioritize the newly developed questionnaires for the criteria by experts in terms of their relative impotence, subjectivity, and uncertainty of human assessment are taken into account fuzzy set theory in a fuzzy environment.
3. From the proposed method, fuzzy AHP helps to find out that the maintenance management plan and maintenance management teams are better practiced in the maintenance management of the Ethiopian Roads Authority as agreed by the decision experts followed by maintenance information and communication management under the main categories of dimension of pavement maintenance management practices. On the contrary, maintenance controlling management and maintenance identification and assessment were identified as rarely practiced Ethiopian Roads Authority.
4. The study also concluded that the top five pavement maintenance management practices mostly practiced in the Ethiopian roads authority were written maintenance management plan (0.072), maintenance staff training (0.071), maintenance management team leader (0.069), maintenance checklists (0.068), and periodic maintenance (0.063).
5. The finding of this study motivates the authors to formulate recommendations to advance the practice of managing pavement maintenance.
6. The authors recommended that the findings of the current study confirm that the fuzzy AHP technique is a powerful tool for evaluating MCDM regarding maintenance management practice.
7. The maintenance staff members of the Ethiopian Roads Authority should be taken into consideration and put in more effort and attention in maintenance identification, maintenance assessment, and control. The maintenance staff should properly organize the maintenance documents, and revise the maintenance plan and schedule for developing their understanding and awareness. The staff members in the maintenance district should be properly supervised and record-keeping on road maintenance activities.
8. The paper provides a supportive practical solution for decision-makers in pavement maintenance management practice to enhance and improve their maintenance practices in managing the maintenance of road construction.
Abbreviations

AHP

Analytical Hierarchy Process

BNP

Best Non-fuzzy Value

ERA

Ethiopian Roads Authority

KMO

Kaiser-meyer-olkin

CI

Consistency Index

CR

Consistency Ratio

DMP

Decision-making Problem

EV

Eigenvalues

MCDMM

Multi Criteria Decision Making Methods

RI

Random Index

TFN

Triangular Fuzzy Number

Author Contributions
Girmay Getawa Ayalew: Conceptualization, Data curation, Formal Analysis, Investigation, Methodology, Software, Validation, Visualization, Writing – original draft, Writing – review & editing
Genet Melkamu Ayalew: Data curation, Formal Analysis, Methodology, Software, Validation, Visualization, Writing – original draft, Writing – review & editing
Zenawi Mehari Limenih: Data curation, Methodology, Software, Validation, Visualization, Writing – review & editing
Meseret Getnet Meharie: Methodology, Software, Supervision, Validation, Visualization, Writing – review & editing
Funding
The authors declare that no funds, grants, or other support were received during the preparation of this manuscript.
Data Availability Statement
The data used to support the findings of this study are available from the corresponding author upon request.
Conflicts of Interest
The authors declare no conflicts of interest.
References
[1] S. I. Sarsam, “Pavement Maintenance Management System : A Review Pavement Maintenance Management System : A Review,” no. September, 2016.
[2] T. R. Aleti, “Developing a pavement management system using data fusion of physical features,” no. april, 2014.
[3] M. G. Augeri, S. Greco, and V. Nicolosi, “Planning urban pavement maintenance by a new interactive multiobjective optimization approach,” vol. 9, 2019.
[4] C. Donnges, G. Edmonds, and B. Johannessen, Rural Road Maintenance: Sustaining the Benefits of Improved Access. 2007.
[5] J. N. Mkilania, “Factors affecting best maintenance practice in Tanzania public sector,” Int. J. Mech. Eng. Technol., vol. 7, no. 3, pp. 139–149, 2016.
[6] A. Salonen, Formulation of Maintenance, no. 100. 2009.
[7] S. G. Mong, S. F. Mohamed, and M. S. Misnan, “Maintenance management model: An identification of key elements for value-based maintenance management by local authority,” Int. J. Eng. Technol., vol. 7, no. 3, pp. 35–43, 2018,
[8] N. Karia, “Exploring Maintenance Management in Service Sector : a Case Study,” Proc. 2014 Int. Conf. Ind. Eng. Oper. Manag. Bali, Indones. January 7 – 9, 2014 Explor., pp. 3119–3128, 2014.
[9] Yunnan and R. R. P. Prc, “Road Sector Maintenance Strategy,” no. i, pp. 1–6.
[10] A. Sachdev and J. Agrawal, “Application of Policy Deployment and Daily Management in service sector,” Int. J. Qual. Innov., vol. 3, no. 1, pp. 1–17, 2017,
[11] E. J. Tucker, “Strategy Implementation in Organizations: A Conceptual Overview,” vol. 14, no. Allio 2005, pp. 205–218, 2016.
[12] J. J. Zhang, “BSI Standards Publication Maintenance Maintenance terminology,” 2010.
[13] H. Larsson and H. Larsson, “An analysis of maintenance strategies and development of a model for strategy formulation Department of Product and Production Development,” 2012.
[14] A. S. Bonde and A. C. Fulzele, “The Organization and management of maintenance function and its effect Over Economies of an Industry,” vol. 3, no. 2, pp. 1152–1155, 2013.
[15] A. Rastegari, “Strategic Maintenance Management in Lean Environment,” 2012.
[16] R. Grimes, “Strategic Maintenance Management 101 : An Introduction to What, Why and How Credit : 6 PDH,” no. 877.
[17] R. Simek, “Development and Infrastructure Roads Management and Maintenance Plan,” 2018.
[18] I. Nedevska, S. Ognjenović, and A. Pustovgar, “Review on the Pavement-repairing Measures as a Condition for the Choice of Road-Maintenance Strategy,” MATEC Web Conf., vol. 106, 2017,
[19] Zurich, “Developing an effective maintenance management program,” Zurich Serv. Corp., vol. 1, no. August, pp. 1–4, 2012.
[20] S. Mostafa, J. Dumrak, and H. Soltan, “Lean Maintenance Roadmap,” Procedia Manuf., vol. 2, no. February, pp. 434–444, 2015,
[21] S. Shakeel and E. A. K. Duggal, “Development of Pavement Maintenance Management System for Chandigarh City Roads,” pp. 1871–1874, 2020.
[22] S. G. Mong, S. F. Mohamed, and M. S. Misnan, “Current issues and barriers of maintenance management practices for public facilities in Malaysia,” Int. J. Eng. Adv. Technol., vol. 8, no. 5, pp. 119–125, 2019,
[23] A. Naji, Z. Beidouri, and M. Oumami, “Maintenance Management And Innovation In Industries : A And Innovation In Industries : A Survey Of Moroccan Companies,” vol. 4, no. 2, 2016.
[24] A. Parida and U. Kumar, “Maintenance Productivity and Performance Measurement,” 2007.
[25] Z. Satovic, “Department of production engineering maintenance engineering and management”.
[26] O. M. Mohamed, “Identifying the barriers affecting quality in maintenance within Libyan manufacturing organisations (public sector),” no. February, p. 260, 2005, [Online]. Available:
[27] G. Willems, “Development and Infrastructure Roads Management and Maintenance Plan,” 2018.
[28] H. Fan, “Rural Road Maintenance In China,” no. 81, pp. 52–68, 2011.
[29] M. Sabure, “The influence of inventory control management system on,” no. January, 2020.
[30] A. Tubis and S. Werbińska-Wojciechowska, “Concept of controlling for maintenance management performance: A case study of passenger transportation company,” Saf. Reliab. Complex Eng. Syst. - Proc. 25th Eur. Saf. Reliab. Conf. ESREL 2015, no. September, pp. 1055–1063, 2015,
[31] R. S. Velmurugan and T. Dhingra, “Maintenance strategy selection and its impact in maintenance function: A conceptual framework,” Int. J. Oper. Prod. Manag., vol. 35, no. 12, pp. 1622–1661, 2015,
[32] W. Nurul, H. Wan, S. A. Othman, M. Ramli, S. Aqilah, and A. Rashid, “Utilizing the Fuzzy Analytical Hierarchy Process (FAHP) Approach to Identify the Best Online Food Delivery Services,” vol. 9, no. 1, pp. 1–12, 2023.
[33] S. Saghafian and S. R. Hejazi, “Multi-criteria group decision making using a modified fuzzy TOPSIS procedure,” Proc. - Int. Conf. Comput. Intell. Model. Control Autom. CIMCA 2005 Int. Conf. Intell. Agents, Web Technol. Internet, vol. 2, pp. 215–220, 2005,
[34] A. A. Jowkar, H. Derakhshanian, M. H. Hoseini, and Z. A. Rahmani, “A factor analysis of identifying the customer behavior patterns : A case study in Tehran,” vol. 2, no. 3, pp. 1347–1353, 2013.
[35] S. Sharma and A. Gupta, “Analysis of Factors Affecting Cost and Time Overruns in Construction,” no. January, 2021,
[36] N. Shrestha, “Factor Analysis as a Tool for Survey Analysis,” no. January, 2021,
[37] A. Niranjan, “TRACE : Tennessee Research and Creative Exchange A Factor Analysis Methodology for Analyzing the Factors that Contribute to Economic Development in the state of Tennessee,” 2004.
[38] R. Mosadeghi, J. Warnken, and R. Tomlinson, “Comparison of Fuzzy-AHP and AHP in a spatial multi- criteria decision making model for urban land-use planning,” vol. 49, no. 2015, pp. 54–65,
[39] R. D. F. S. M. Russo and R. Camanho, “Criteria in AHP: A systematic review of literature,” Procedia Comput. Sci., vol. 55, no. Itqm, pp. 1123–1132, 2015,
[40] A. Çebİ and H. Karal, “An application of fuzzy analytic hierarchy process (FAHP) for evaluating students ’ project,” vol. 12, no. 3, pp. 120–132, 2017,
[41] G. G. Ayalew, L. A. Alemneh, and G. M. Ayalew, “Exploring fuzzy AHP approaches for quality management control practices in public building construction projects,” Cogent Eng., vol. 11, no. 1, p., 2024,
[42] A. Basahel and O. Taylan, “Using fuzzy ahp and fuzzy topsis approaches for assessing safety conditions at,” vol. 6, no. 4, pp. 728–745, 2016,
[43] G. Kabir and M. A. A. Hasin, “Evaluation of customer oriented success factors in mobile commerce using fuzzy AHP,” vol. 4, no. 2, pp. 361–386, 2013,
[44] F. Mulubrhan, A. A. Mokhtar, and M. Muhammad, “Comparative Analysis between Fuzzy and Traditional Analytical Hierarchy Process,” vol. 6, pp. 0–4, 2014.
[45] H. Huang and C. Ho, “Applying the Fuzzy Analytic Hierarchy Process to Consumer Decision-Making Regarding Home Stays,” vol. 5, no. February 2013, 2016,
[46] G. G. Ayalew, G. M. Ayalew, and M. G. Meharie, “Integrating exploratory factor analysis and fuzzy AHP models for assessing the factors affecting the performance of building construction projects : The case of Ethiopia,” Cogent Eng., vol. 10, no. 1, 2023,
[47] C. C. Sun, “A performance evaluation model by integrating fuzzy AHP and fuzzy TOPSIS methods,” Expert Syst. Appl., vol. 37, no. 12, pp. 7745–7754, 2010,
[48] M. Askari, H. R. Shokrizadeh, and N. Ghane, “A Fuzzy AHP Model in Risk Ranking,” vol. 6, no. 14, pp. 194–203, 2014.
[49] H. Fu, Y. Chen, and G. Wang, “Using a Fuzzy Analytic Hierarchy Process to Formulate an E ff ectual Tea Assessment System,” 2020.
[50] D. J. Simjanović, N. O. Vesić, B. M. Randjelović, and D. Vujadinović, “Cyber Security Criteria : Fuzzy AHP approach,” no. 1, 2023.
[51] G. G. Ayalew, M. G. Meharie, and B. Worku, “A road maintenance management strategy evaluation and selection model by integrating Fuzzy AHP and Fuzzy TOPSIS methods : The case of Ethiopian Roads Authority: The case of,” Cogent Eng., vol. 9, no. 1, 2022,
Cite This Article
  • APA Style

    Ayalew, G. G., Ayalew, G. M., Limenih, Z. M., Meharie, M. G. (2025). A Hybrid Approach Based on Factor Analysis and Fuzzy AHP Multi-criteria Decision-Making Model for Evaluating Pavement Maintenance Management Practices: The Case of Ethiopian Roads Authority. Journal of Civil, Construction and Environmental Engineering, 10(4), 131-152. https://doi.org/10.11648/j.jccee.20251004.11

    Copy | Download

    ACS Style

    Ayalew, G. G.; Ayalew, G. M.; Limenih, Z. M.; Meharie, M. G. A Hybrid Approach Based on Factor Analysis and Fuzzy AHP Multi-criteria Decision-Making Model for Evaluating Pavement Maintenance Management Practices: The Case of Ethiopian Roads Authority. J. Civ. Constr. Environ. Eng. 2025, 10(4), 131-152. doi: 10.11648/j.jccee.20251004.11

    Copy | Download

    AMA Style

    Ayalew GG, Ayalew GM, Limenih ZM, Meharie MG. A Hybrid Approach Based on Factor Analysis and Fuzzy AHP Multi-criteria Decision-Making Model for Evaluating Pavement Maintenance Management Practices: The Case of Ethiopian Roads Authority. J Civ Constr Environ Eng. 2025;10(4):131-152. doi: 10.11648/j.jccee.20251004.11

    Copy | Download

  • @article{10.11648/j.jccee.20251004.11,
      author = {Girmay Getawa Ayalew and Genet Melkamu Ayalew and Zenawi Mehari Limenih and Meseret Getnet Meharie},
      title = {A Hybrid Approach Based on Factor Analysis and Fuzzy AHP Multi-criteria Decision-Making Model for Evaluating Pavement Maintenance Management Practices: The Case of Ethiopian Roads Authority
    },
      journal = {Journal of Civil, Construction and Environmental Engineering},
      volume = {10},
      number = {4},
      pages = {131-152},
      doi = {10.11648/j.jccee.20251004.11},
      url = {https://doi.org/10.11648/j.jccee.20251004.11},
      eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.jccee.20251004.11},
      abstract = {The construction industry has long been realized as one of the most important enablers for the social, economic, and political development of countries. Road pavement that has been constructed undergoes a process of deterioration and catastrophic failure after opening to traffic starts at a low rate and with time this rate increases because of aging, overuse, misuse, and mismanagement. Proper maintenance management practice helps to reduce the cost of maintenance and to make sure the pavement is in good condition with minimum maintenance. Thus, the study focuses on exploring the pavement maintenance management practice in the Ethiopian road authority. The method of data analysis for this study was carried out by using factor analysis and fuzzy AHP methods. Factor analysis provides as to reduce a data set to a more manageable size without much loss of the original information while fuzzy AHP is used to determine the preference weights of the variables. To achieve the objective, the data were collected from primary and secondary sources. SPSS software version 23, and Microsoft Excel were used as analysis tools. The study revealed that written maintenance management plans (0.072), maintenance staff training (0.071), maintenance management team leader (0.069), maintenance checklists (0.068), and periodic maintenance (0.063) were mostly practiced in the Ethiopian road authority. Finally, it can be recommended that the decision-makers conduct practical solutions to enhance, advance, and improve pavement maintenance management practices.},
     year = {2025}
    }
    

    Copy | Download

  • TY  - JOUR
    T1  - A Hybrid Approach Based on Factor Analysis and Fuzzy AHP Multi-criteria Decision-Making Model for Evaluating Pavement Maintenance Management Practices: The Case of Ethiopian Roads Authority
    
    AU  - Girmay Getawa Ayalew
    AU  - Genet Melkamu Ayalew
    AU  - Zenawi Mehari Limenih
    AU  - Meseret Getnet Meharie
    Y1  - 2025/07/10
    PY  - 2025
    N1  - https://doi.org/10.11648/j.jccee.20251004.11
    DO  - 10.11648/j.jccee.20251004.11
    T2  - Journal of Civil, Construction and Environmental Engineering
    JF  - Journal of Civil, Construction and Environmental Engineering
    JO  - Journal of Civil, Construction and Environmental Engineering
    SP  - 131
    EP  - 152
    PB  - Science Publishing Group
    SN  - 2637-3890
    UR  - https://doi.org/10.11648/j.jccee.20251004.11
    AB  - The construction industry has long been realized as one of the most important enablers for the social, economic, and political development of countries. Road pavement that has been constructed undergoes a process of deterioration and catastrophic failure after opening to traffic starts at a low rate and with time this rate increases because of aging, overuse, misuse, and mismanagement. Proper maintenance management practice helps to reduce the cost of maintenance and to make sure the pavement is in good condition with minimum maintenance. Thus, the study focuses on exploring the pavement maintenance management practice in the Ethiopian road authority. The method of data analysis for this study was carried out by using factor analysis and fuzzy AHP methods. Factor analysis provides as to reduce a data set to a more manageable size without much loss of the original information while fuzzy AHP is used to determine the preference weights of the variables. To achieve the objective, the data were collected from primary and secondary sources. SPSS software version 23, and Microsoft Excel were used as analysis tools. The study revealed that written maintenance management plans (0.072), maintenance staff training (0.071), maintenance management team leader (0.069), maintenance checklists (0.068), and periodic maintenance (0.063) were mostly practiced in the Ethiopian road authority. Finally, it can be recommended that the decision-makers conduct practical solutions to enhance, advance, and improve pavement maintenance management practices.
    VL  - 10
    IS  - 4
    ER  - 

    Copy | Download

Author Information
  • School of Civil and Water Resource Engineering, Department of Construction Technology and Management, Woldia University, Woldia, Ethiopia

    Biography: Girmay Getawa Ayalew is currently a lecturer at the Woldia Institute of Technology, Woldia University, Woldia, Ethiopia. He is former a lecturer at the Gondar Institute of Technology, University of Gondar, Gondar, Ethiopia. He received his BSc degree in Construction Tech-nology and Management from Woldia University and his MSc degree in Construction Engineering and Management from the University of Gondar with first-class honours with very great distinction. He has an extensive experience in multiple publications and patents. He is participated in different peer-reviewed articles as a reviewer and was recognized as a trusted reviewer with a high level of peer review com-petency. Now he is 6 years of experience in teaching and researching. His research interest includes BIM, Machine Learning Algorithms, Fuzzy Logic Regression Modelling, Sustainability in Construction, Facility Management, and Project Management, Material Management and TQM.

  • School of Civil and Water Resource Engineering, Department of Construction Technology and Management, Woldia University, Woldia, Ethiopia

    Biography: Genet Melkamu Ayalew is currently a lecturer at the Woldia Institute of Technology, Woldia University, Woldia, Ethiopia. She is former a lecturer at the Gondar Institute of Technology, University of Gondar, Gondar, Ethiopia. She received her MSc degree in Construction Engineering and Management from the University of Gondar, Ethiopia. Currently she has 6 years of teaching experience and actively engaged in research. She published more than five research papers in highly indexed peer-reviewed journals. Her research interest includes Project Performance, Project Management, BIM, MLA, Maintenance Management, Fuzzy AHP, and Regression Modeling.

  • School of Architecture and Construction Technology and Management, Department of Construction Technology and Management, Institute of Technology, University of Gondar, Gondar, Ethiopia

    Biography: Zenawi Mehari Limenih is a lecturer at the Gondar Institute of Technology, University of Gondar, Gondar, Ethiopia. He received his MSc degree in Civil Engineering (Construction Technology and Management) from Addis Ababa Science and Technology University, Addis Ababa, Ethiopia. He trained entrepreneurship in 2017, at jig jiga university, Higher educational meeting in 2014 at Debre Markos university, Leadership training in 2017 at Jig Jiga university, Trade work management in 2017 at Debre Markos poly technic college, Induction training in 2018 at university of Gondar, Higher diploma program (HDP) in 2018 at University of Gondar, Building information modelling (BIM) in 2022 at Addis Ababa Science and Technology university and Python software training in 2025 at University of Gondar. His research interest includes Construction management, Sustainability in construction, Construction Technology, Modern Construction, and Construction law.

  • School of Civil Engineering and Architecture, Department of Civil Engineering, Adama Science and Technology University, Adama, Ethiopia

    Biography: Meseret Getnet Meharie (Ph.D.) is a senior lecturer at Adama Science and Technology University, Adama, Ethiopia. He is an Assistant professor at Adama Science and Technology University, Adama, Ethiopia. His research interest includes Cost Estimation of Construction Projects, Maintenance management, Fuzzy AHP, and Machine learning algorithm in predicting the cost of highway projects.