Project Management Practice in Groundwater Construction Project in Ghana

Received: 14 September 2018    Accepted: 26 October 2018    Published: 26 November 2018
Views:       Downloads:

Share This Article

Abstract

The implementation of good project management practice effectively, is a way of improving future projects especially in groundwater construction projects. The lack of good project management principles may cause project delays, and higher costs. A fundamental principle of project management is that any project, regardless of its size or type, consists of three components: scope, budget, and schedule. The purpose of this paper is to investigate and examine how project Management practice in groundwater construction projects in Ghana. The research focuses on the issues of management practice in groundwater construction projects in order to recommend ways of improving management practices. The data were collected through a questionnaire survey sent to the managers, consultants and client’s representative who had been involved in the construction of groundwater projects in Ghana. The survey covered the project management lifecycle: project initiation, planning, executing, monitoring/controlling the closing/evaluating processes of the project. The result of the data analysis reveals that: all three groups (managers, consultant and clients representative) generally agreed that most of the problems in the groundwater construction projects are human and management related. Furthermore, the results indicated that most of the projects did not have project management processes and procedures. The paper concludes with recommendations that the scope of the project is defined and a project management plan is developed be taken in the early stages (conceptual and planning, and evaluating phases) of the groundwater construction projects.

DOI 10.11648/j.ajmse.20180305.14
Published in American Journal of Management Science and Engineering (Volume 3, Issue 5, September 2018)
Page(s) 60-68
Creative Commons

This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited.

Copyright

Copyright © The Author(s), 2024. Published by Science Publishing Group

Keywords

Project Management Practice, Groundwater, Construction, Ghana

References
[1] Bagayal, O., and Song, J., 2016, Empirical Study of Factors Influencing Schedule Delays of Public Construction Projects in Burkina Faso, Journal of Management in Engineering, Vol. 32, Issue 5.
[2] Ghana Statistical Service, Data Production Unit, (2016), 2010 Ghana Population Projection by Sex, 2010-2016 http://www.statsghana.gov.gh/docfiles/2010phc/Projected%20population%20by%20sex%202010%20-%202016.pdf.
[3] GYAU-BOAKYE P and DAPAAH-SIAKWAN S. 2000. Groundwater as Source of Rural Water Supply in Ghana, Journal of Applied Science and Technology, Vol. 5, Nos. 1 & 2, pp 77-86, 2000.
[4] GSS, Ghana Living Standards Survey Round 6 (GLSS6), 2014. Main Report. Ghana Statistical Services, Accra.
[5] LAUBE, W., AWO, M. and SCHRAVEN, B., 2008. Erratic Rains and Erratic Markets: Environmental change, economic globalisation and the expansion of shallow groundwater irrigation in West Africa. ZEF Working Paper Series, ISSN 1864-6638. Department of Political and Cultural Change Center for Development Research, University of Bonn.
[6] MOFA, 2004. Projected livestock population for 1997-2007. Ministry of Food and Agriculture, Accra, Ghana.
[7] AGODZO, S. K., 2003. Shallow well irrigation for shallot farming in the Keta Lagoon Area of Ghana. Journal of the Ghana Institution of Engineers. Volume 1, Number 1:pp1-6.
[8] DARKO, P. K., DUA, A. A., and DAPAAH-SIAKWAN, S. 2003. Groundwater Assessment: An element of integrated Water Resources Management: the case of Densu River Basin. Technical Report for the Water Resources Commission, Accra, Ghana.
[9] Grönwall, J., 2016, Self-supply and accountability: to govern or not to govern groundwater for the (peri-) urban poor in Accra, Ghana, Environ Earth Science 75(6), p.1163.
[10] Chakava Y, Franceys R, Parker A., 2014, Private boreholes for Nairobi’s urban poor: the stop-gap or the solution? Habitat International Vol. 43, pp. 108–116.
[11] Grönwall J T, Mulenga M, McGranahan G., 2010, Groundwater, self-supply and poor urban dwellers A review with case studies of Bangalore and Lusaka. IIED Human Settlements Working Paper Series, Water and Sanitation, 26, November 2010 http://pubs.iied.org/pdfs/10584IIED.pdf.
[12] Okotto L, Okotto-Okotto J, Price H, Pedley S, Wright J., 2015, Socio-economic aspects of domestic groundwater consumption, vending and use in Kisumu, Kenya. Appl Geography Vol. 58 pp. 189–197.
[13] QUARTY, Jr., E. L., (1996). “Development Project through Build-Operate Schemes: their Role and Place in Developing Countries”. International Journal of Project Management. 1996, Vol. 14, No. 1, pp. 47-52.
[14] PMI, “A Guide to the Project Body of Knowledge” (PMBOK) Project Management Institute (1996).
[15] ASTON, B. 2016, Project Management Life Cycle: The Complete Guide, https://thedigitalprojectmanager.com/project-management-life-cycle/.
[16] ProjectCubicle, 2018, Project Life Cycle Phases for Project Management https://www.projectcubicle.com/five-project-life-cycle-phases/.
[17] ENDE, L. D. and MARREWIJK A. 2014, The ritualization of transitions in the project life cycle: A study of transition rituals in construction projects, International Journal of Project Management, Vol. 32, Issue 7, pp. 1134-114
[18] GOLINIA, R., KALCHSCHMIDTA, M. and LANDONIB, P. 2015, Adoption of project management practices: The impact on international development projects of non-governmental organizations, International Journal of Project Management, Vol. 33, Issue 3, pp. 650-663.
[19] MUSPRATT, M. (1987). “Conditions Affecting Project in Less Developed Countries”. Project Management. Vol. 5, No. 1, pp. 45-53.
[20] CODAS, M. (1987). “Development of project Management in Brazil – a Historical Overview”. Project Management. Vol. 5, No. 3, pp. 144-148.
[21] CASH, C. and ROBERTS, F. (1992). “Elements of successful project Management”. Journal of Systems Management. 1992, pp. 10-12.
[22] ABBASI, G. Y. and AL-MHARMAH, H. A. (2000) “Project Management Practice by the Public Sector in Developing Country”. International Journal of Project Management. Vol. 18, No. 2, pp. 105-109.
[23] KWAK, Y. H., SADATSAFAVI, H., WALEWSKI, J., and WILLIAMS, N. L., 2015, Evolution of project based organization: A case study, International Journal of Project Management, Vol. 33, Issue 8, pp. 1652-1664.
[24] VAN DER WESTHUIJZEN, D. and PELPOLA, K., 1994. Project management of borehole programme. IN: Pickford, J. et al. (eds). Affordable water supply and sanitation: Proceedings of the 20th WEDC International Conference, Colombo, Sri Lanka, 22-26 August 1994, pp.124-127.
[25] BLACK, K. (1996). “Causes of project Failure: A survey of Professional Engineers”. PM Network, November 1996, pp. 21-24.
[26] DUFFY, P. J. and THOMAS, R. D. (1989). “Project Performance Auditing”. Project Management. Vol. 7, No. 2, May 1989, pp. 101-104.
[27] ZOHREHVANDI, S., KHALILZADEH, M., HAJIZADEHB, M., and CHERAGHI, E., 2017, Planning project closure phase in combined cycle power plant projects, Procedia Computer Science, Vol. 121, pp. 274-281.
Cite This Article
  • APA Style

    Yaw Frimpong, Jacob Oluwoye. (2018). Project Management Practice in Groundwater Construction Project in Ghana. American Journal of Management Science and Engineering, 3(5), 60-68. https://doi.org/10.11648/j.ajmse.20180305.14

    Copy | Download

    ACS Style

    Yaw Frimpong; Jacob Oluwoye. Project Management Practice in Groundwater Construction Project in Ghana. Am. J. Manag. Sci. Eng. 2018, 3(5), 60-68. doi: 10.11648/j.ajmse.20180305.14

    Copy | Download

    AMA Style

    Yaw Frimpong, Jacob Oluwoye. Project Management Practice in Groundwater Construction Project in Ghana. Am J Manag Sci Eng. 2018;3(5):60-68. doi: 10.11648/j.ajmse.20180305.14

    Copy | Download

  • @article{10.11648/j.ajmse.20180305.14,
      author = {Yaw Frimpong and Jacob Oluwoye},
      title = {Project Management Practice in Groundwater Construction Project in Ghana},
      journal = {American Journal of Management Science and Engineering},
      volume = {3},
      number = {5},
      pages = {60-68},
      doi = {10.11648/j.ajmse.20180305.14},
      url = {https://doi.org/10.11648/j.ajmse.20180305.14},
      eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.ajmse.20180305.14},
      abstract = {The implementation of good project management practice effectively, is a way of improving future projects especially in groundwater construction projects. The lack of good project management principles may cause project delays, and higher costs. A fundamental principle of project management is that any project, regardless of its size or type, consists of three components: scope, budget, and schedule. The purpose of this paper is to investigate and examine how project Management practice in groundwater construction projects in Ghana. The research focuses on the issues of management practice in groundwater construction projects in order to recommend ways of improving management practices. The data were collected through a questionnaire survey sent to the managers, consultants and client’s representative who had been involved in the construction of groundwater projects in Ghana. The survey covered the project management lifecycle: project initiation, planning, executing, monitoring/controlling the closing/evaluating processes of the project. The result of the data analysis reveals that: all three groups (managers, consultant and clients representative) generally agreed that most of the problems in the groundwater construction projects are human and management related. Furthermore, the results indicated that most of the projects did not have project management processes and procedures. The paper concludes with recommendations that the scope of the project is defined and a project management plan is developed be taken in the early stages (conceptual and planning, and evaluating phases) of the groundwater construction projects.},
     year = {2018}
    }
    

    Copy | Download

  • TY  - JOUR
    T1  - Project Management Practice in Groundwater Construction Project in Ghana
    AU  - Yaw Frimpong
    AU  - Jacob Oluwoye
    Y1  - 2018/11/26
    PY  - 2018
    N1  - https://doi.org/10.11648/j.ajmse.20180305.14
    DO  - 10.11648/j.ajmse.20180305.14
    T2  - American Journal of Management Science and Engineering
    JF  - American Journal of Management Science and Engineering
    JO  - American Journal of Management Science and Engineering
    SP  - 60
    EP  - 68
    PB  - Science Publishing Group
    SN  - 2575-1379
    UR  - https://doi.org/10.11648/j.ajmse.20180305.14
    AB  - The implementation of good project management practice effectively, is a way of improving future projects especially in groundwater construction projects. The lack of good project management principles may cause project delays, and higher costs. A fundamental principle of project management is that any project, regardless of its size or type, consists of three components: scope, budget, and schedule. The purpose of this paper is to investigate and examine how project Management practice in groundwater construction projects in Ghana. The research focuses on the issues of management practice in groundwater construction projects in order to recommend ways of improving management practices. The data were collected through a questionnaire survey sent to the managers, consultants and client’s representative who had been involved in the construction of groundwater projects in Ghana. The survey covered the project management lifecycle: project initiation, planning, executing, monitoring/controlling the closing/evaluating processes of the project. The result of the data analysis reveals that: all three groups (managers, consultant and clients representative) generally agreed that most of the problems in the groundwater construction projects are human and management related. Furthermore, the results indicated that most of the projects did not have project management processes and procedures. The paper concludes with recommendations that the scope of the project is defined and a project management plan is developed be taken in the early stages (conceptual and planning, and evaluating phases) of the groundwater construction projects.
    VL  - 3
    IS  - 5
    ER  - 

    Copy | Download

Author Information
  • Project Management, Groundwater Services, Sydney, Australia

  • Department of Community and Regional Planning, Alabama A & M University, Alabama, USA

  • Sections